Underground Construction Office Addition

Project Details

Design and construction of 20,000 SF concrete tilt-up office expansion. The foundations and slab-on-grade were completed in five months to use as casting bed for the panel formation of 15 panels. An additional casting bed was constructed for the remaining panels. All 20 panels were tilted in a day. Scope included improvements to the electrical, HVAC and plumbing systems. Two skylights were installed into the new building to maximize daylighting and all of the office lights were equipped with LED lighting to help reduce energy consumption. The lunch room was upgraded and all of the large offices and conference rooms were wired for teleconferencing with televisions. The project was successfully completed while maintaining operational functionality of the existing building.

Owner
Underground Construction
Location
Benicia, CA
Square Feet
20,000
Construction
Concrete Tilt Up