Construction of new process facilities and improvements to the existing wastewater treatment plant. Scope covered full tertiary treatment and biosolids handling facilities. Overaa self-performed all site utilities, 15,000 CY of structural concrete, construction a 45,000 SF solar biosolids drying facility, installation, start-up and commissioning of all process equipment, and all piping installations. We coordinated activities with operations to schedule over 25 plant shutdowns and tie-ins during low flow times without any impact to plant operations. The entire complex was completed one month ahead of the critical path milestone.