Los Esteros Power Plant

Overaa provided sitework, underground utility work, and the concrete foundation work for the Los Esteros Power Plant Expansion in San Jose, CA. Overaa placed a total of approximately 4050 cubic yards of concrete, including 270 cubic yards for the Cooling Tower Basin Slab South. For this foundation, 270 cubic yards were placed at a pace of 60 cubic yards per hour using 27 concrete trucks.