Las Positas College Public Safety Complex & Advanced Manufacturing Transportation Facility

The Public Safety Complex (PSC) and Advanced Manufacturing and Transportation (AMT) Buildings are co-located to allow for shared linkages between programs, classrooms, and training spaces. The PSC features a 2,400 SF, three-story fire training tower, EMS Simulation Lab and Situation Rooms, Fire Training with “Class A” burn areas, and Fire Training Apparatus. The AMT houses […]

Piedmont High School Alan Harvey Theater

Construction of a new 22,700 SF theater complete with stage, 452 seats, drama classroom, green room, restrooms, conference room, and department offices.  The new theater features a large, state-of-the-art auditorium with recessed tiered concrete seating structure, orchestra pits, acoustical paneling, modern A/V system, sound control booth, rigging, curtains, and smoke hatches. Sound-rated acoustical doors and […]

Oakland Unified School District Central Kitchen, Instructional Farm, and Education Center

New 45,000 SF centralized kitchen and food distribution facility that serves the entire Oakland Unified School District. The facility features 40,000 SF of kitchen space plus 5,000 SF of administration offices, classrooms, demonstration prep spaces, administrative support spaces, and 2 acres of farming site.  A horticultural center and culinary learning center were also added. Construction […]

Piedmont High School and Middle School Renovations

Primary scope of work included renovations and seismic improvements for Piedmont High School’s Quad/Library (Building A) and Student Center (Building B). Building A included protection of existing historic type finishes, demolition and abatement, seismic improvements of new hand dug 12’-20’ deep foundations, concrete/shotcrete walls to roof structure for seismic reinforcing, a new roof plywood and […]

Tamalpais High School

Construction and modernization of an existing high school campus. Overaa removed the existing pools and constructed a new swimming pool with a mechanical building. A new site glass elevator tower for accessibility on the mountainous site, a weight room and field house buildings, tennis courts, a basketball court, parking lot, and a student drop off […]

Havens Elementary School – Ellen Driscoll Playhouse

Complete seismic upgrade and interior remodel of an existing playhouse. Scope included the protection of existing historic finishes, additional structural wood framing and concrete foundation for seismic improvements, new roof and fire sprinkler system, and a complete overhaul of interior finishes. We self-performed the extensive wood framing improvements, which was key to making the schedule […]

Edna Maguire New Elementary School

Two phase project that included demolition of the existing elementary campus and construction of the new elementary school. Phase 1 included the set up of portables for interim housing and demolition of existing campus, plus site utility work during an intense 120 day schedule. Student safety was paramount in the planning and construction of the […]

Monta Vista High School New Student Center & Quad Modernization

New 44,200 SF two-story student center plus renovation, reconfiguration, and reconstruction of the student quad and front drop-off area. The new student center features a college-style cafeteria and kitchen equipped with several stove tops, exhaust hoods, refrigerators, and monitor screens to display menus. The facility also houses programming and physics labs, restrooms, an electrical room, […]

John Swett High School, Phase I & II

New Administrative/Classroom Building and Arts Department, plus additions and modernization of an occupied campus. Phase I included modifications and additions to the existing buildings. Extensive interior renovations included: doors; windows; glazing; curtain walls; cabinets; acoustical tile and gypsum board ceilings; bathrooms; finishes including flooring, painting, ceramic tile, other wall coverings and wall base; and replacement […]

Sankofa Academy, Washington Elementary School, Phase I & II

Modernization of a 42,340 SF elementary school building completed in two, eight week sessions over two summer breaks. Scope covered two-stories plus basement cafeteria. 14 classrooms, auditorium, library, warming kitchen, administrative and support spaces, plus a licensed kindergarten were renovated. Additional scope covered site work, electrical systems upgrade, fire alarm replacement, interior finishes and window […]