Valero Flue Gas Scrubber Foundations

Overaa self-performed three mat foundations with pedestals, including anchor bolts and backfill for the Flue Gas Scrubber Equipment. Additionally, Overaa installed four concrete foundations and a 25 ft deep pit for the FGS Large Euipment; the FGS Furnace Foundation and the FGS Substation R & 48 which included 50 concrete pedestals, and two raised 30' x40' slabs.