COVID-19 Update: We are continuing operations with added safety measures

Waste Management Organic Material Processing Facility

The project consisted of the construction of a new organics processing facility which includes pre and post processing facilities, with eight-lane enclosed Smartturn Composting System and covered aeration piping. The 90,000 SF project included construction of facilities on drilled pile foundations on top of a landfill site. The Overaa design-build  team was responsible for coordination of all design and construction of building facilities including sitework, drilled piles, building foundations, structural concrete for foundations and lane turners walls, process aeration piping, building HVAC and electrical work. The team was also responsible for preparation and coordination of all permit packages through the City of San Leandro.