LBNL Advanced Light Source User Support Building

Design and construction of a LEED Gold facility that supports LBNL’s Advance Light Source (ALS) Building, which houses a specialized particle accelerator that generates bright beams of x-ray light for scientific research. The new 31,000 SF facility contains staging for experiments, labs, storage spaces, conference rooms and offices. Construction is slab-on-grade, light/heavy gauge metal framing […]

Stanford Linear Accelerator Research Building 52

Design and construction of a 64,000 SF, LEED Gold office building that houses Stanford’s control room for the multiple accelerators on its campus. The structural design for the new building was based on a sustainable, integrated systems approach. Construction included a unique rain screen system that utilizes a Norwegian weatherproof material. The outside wall was […]

Army Reserve Center Concord

Design and construction of a new 64,000 SF Army Reserve Center (ARC), 9,500 SF Organizational Maintenance Shop (OMS), and 4,000 SF unheated storage building. The project is LEED Gold certified and features a 87,000 SF photovoltaic field that generates about 465 kilowatts of electricity directly tied into the new training and storage building’s electrical system. […]

VA Mather Behavioral Health Inpatient Unit

Design and construction of a 14,127 SF behavioral health inpatient unit on an occupied Air Force Base. The LEED Silver facility includes a combination of secure single and double secure patient rooms, as well as administrative, support, and service areas. Project site improvements included parking lots, sidewalks, landscaping and security features. The foundation and roof deck […]

Kaiser Oakland Medical Center Parking Structure Phase 2

Design and construction of a 410,000 SF parking structure directly across from an operating Medical Office Building (MOB). The ten-level (two below grade), 1,220 stall facility is comprised of a pre-cast hybrid structural system. It features a mat slab foundation, waterproofed basement levels, metal panels, and perforated metal screening. Overaa self-performed the 7,000 cubic yard […]

Ohlone Community College District Parking Structure

New cast-in-place parking structure on a occupied college campus. Scope covered demolition and construction of a new five-level, 300,000 SF parking facility complete with 905 stalls, plus a pedestrian sidewalk and turnaround that connects the structure to the campus. The project contributes to the campus’ sustainability goals including net-zero energy consumption. Self-performed work included general […]

Willie L. Brown, Jr. Middle School

Design and construction of a new middle school campus. New construction consisted of 88,500 SF of space within two new structures. This includes a new 60,800 GSF, three-story building containing classrooms, administration, wellness center, multi-purpose room, library, kitchen, and associated support spaces and facilities. A new 28,200 GSF, two-story building houses additional classrooms, performing arts […]

Stranda Apartments

New 4-level, mixed retail and apartment building in downtown Berkeley. Property features ground level retail space, 21 apartments, rooftop communal space, and below ground elevated lift garage.

Albany Public Works Service Center

Design and construction of two structures on an approximately one-acre site. The main two-story building is a 16,000 SF pre-engineered steel structure with metal siding and an elevated concrete deck. The first floor is designated for the fleet program and features a warehouse and various shops. The second floor consists of office space that features […]

Serramonte Center Parking Structure

Design and construction of a 457,000 SF cast-in-place parking structure for a super-regional shopping mall. The 1,372 stall, five-level facility features a second-level pedestrian bridge with elegant glass railing system that connects to the mall. Four EV charging stations and provisions for 94 additional stalls were provided. Scope also covered utility relocation and site preparation. […]