Bayer Compressed Dry Air Facility

Project Details

Construction of a brand new Compressed Dry Air Facility (CDA) generation facility. Scope included the installation of two new compressor units, the relocation of a third unit, one aftercooler system, one wet receiver, 2 dryers, one dry receiver, and a series of high performance filter units. Extensive CDA piping distribution system from the new facility to the existing manufacturing plant was provided on overhead utility racks. The exterior is finished with two complimentary architectural paneling systems to tie in the colors and styles of the surrounding buildings on campus. A large storefront assembly clearly displays this new industrial showpiece, which is located at one of the campus’ busiest entrances.

Owner
Confidential Client
Location
Berkeley, CA