Bid Details for WCWD Secondary Sedimentation Basin Upgrades Project – Short-term Improvements For Basins (1) & (2)

Project
WCWD Secondary Sedimentation Basin Upgrades Project – Short-term Improvements For Basins (1) & (2)
Owner
WEST COUNTY WASTEWATER PROJECT (WCWD)
Bid Time
12/16/2026 3:00 pm
Description

The work covered by this contract will be performed in Richmond, CA. The work includes, but is not
limited to, the following:
1. Sedimentation Basin No. 1 (SSB No. 1):
a. Procurement of the equipment for SSB No.1 will be covered by the Owner
under a separate Procurement Contract. Contractor shall install
Owner procured equipment for SSB No.1.
b. Removal and replacement of the No. 3 water system, including piping, valves,
supports, hose reel system, and appurtenances.
c. Removal and replacement of 18 precast concrete walkway panels along SSB
Nos. 1 and 2 (as shown on the Drawings), replaced in kind.
d. Removal and replacement of two sluice gates along SSBs Nos. 1 and 2 (as
shown on the Drawings).
e. Miscellaneous concrete surface restoration and crack repair.
f. Upgrades to electrical components, including modifications to existing
electrical systems to support new collector equipment and integration with the
existing control system.
2. Sedimentation Basin No. 2 (SSB No. 2):
a. Procurement of the equipment for SSB No.2 will be covered by the Owner
under a separate Procurement Contract. Contractor shall install
Owner procured equipment for SSB No.2.
b. Removal and replacement of existing chain-and-flight mechanisms and
accessories, including drives, motors, wall bearing supports, sprockets, flights,
shafts, and chains.
c. Removal and replacement of the No. 3 water system, including piping, valves,
supports, hose reel system, and appurtenances.
d. Removal and replacement of 18 precast concrete walkway panels along SSB
Nos. 1 and 2 (as shown on the Drawings), replaced in kind.

e. Removal and replacement of two sluice gates along SSBs Nos. 1 and 2 (as
shown on the Drawings).
f. Miscellaneous concrete surface restoration and crack repair.
g. Upgrades to electrical components, including modifications to existing
electrical systems to support new collector equipment and integration with the
existing control system.
3. Contractor shall perform all cleaning of SSBs No. 1 and 2 necessary to achieve
sanitary working conditions and to prepare surfaces for required tasks.
Contractor shall include sufficient time in the schedule to perform the cleaning, and
no delay shall be claimed.
4. The existing facility must be always kept in operation.

 

Project Stabilization Labor Agreement

 

West County Wastewater has established the following
goals for employment of West County Wastewater Residents:
1. At least 50% of the total work hours for the West County Wastewater Project shall be
performed by West County Residents.
2. At least 50% of New Hires for the West County Wastewater Project shall be West County
Residents for the duration of the West County Project.

 

Location
Richmond, CA.
Amount
$ 5,625,000
Bid Walk

A Mandatory on-site pre-bid meetings to discuss the project will be held as follows:
– November 10th, 2026 at 10:00 AM
– November 12th, 2026 at 10:00 AM
Interested contractors are required to attend one of the two meetings above. Please contact
Mohammed Masoud (mmasoud@wcwd.org) at 510-407-9563

Requirements
In accordance with Labor Code section 1725.5, all participating contractors and subcontractors must be registered with the Public Works Contractor Registration program established by the Department of Industrial Relations. Please take notice that, the Project will be subject to the Project Stabilization Labor Agreement for the West County Wastewater, effective January 1, 2021 (“PSLA”). Contractor and all of its subcontractors of all tiers shall be bound by the PSLA by signing the Agreement to be Bound that is attached as Attachment A to the PSLA and returning all signed copies to the West County Wastewater. West County Wastewater has established the following goals for employment of West County Wastewater Residents: 1. At least 50% of the total work hours for the West County Wastewater Project shall be performed by West County Residents. 2. At least 50% of New Hires for the West County Wastewater Project shall be West County Residents for the duration of the West County Project.
Availability
Contract Documents are available at the OPENGOV Website at https://www.opengov.com. Inquiries regarding further information about the Project may be directed to Mohammed Masoud (mmasoud@wcwd.org) at 510-407-9563.