General Work Description: The work consists of dewatering the Water Reclamation Facility’s
aeration basin, further excavation and installation of a new concrete aeration basin facility with a
flow splitting structure, air lines, diffusers, a mixing system, a surface wasting pumping system,
and a high flow return pump connected to the adjacent high flow storage pond. In conjunction with
the new aeration basin, a new blower building with internal blowers will be constructed with a
separate electrical control building. Additional work includes a separate carbon feed building with
internal tanks and chemical metering pumps, a below grade secondary clarifier weir flow splitting
structure, and relocation of a concrete sand filter high flow diversion structure.