Location, Description, and Completion of Work: This project is located at the City of Folsom Water Treatment Plant located at 194 Randall Drive, Folsom, CA. The work to be done is shown on the Plans, and generally consists of, but is not limited to, furnishing all labor, materials, and equipment to install pumping facilities; all trenching and backfilling; all piping; all paving, at-grade improvements; all structural facilities, all geotechnical work, all site work and grading; all electrical, instrumentation and control; and all miscellaneous work as shown on the Contract Drawings and included in the project documents.
All work shall be completed within 480 calendar days after the date of the written Notice to Proceed from the TOLL BROS., INC