Scope:
· The design build project includes the replacement of existing buildings and the construction of a new administration and classrooms building (approximately 40,000 sf) and the construction of a new gymnasium (approximately 8,000 sf).
· Traditional wood framed structures.
MEPF:
· Design build by the Subcontractors, you will carry the EOR and pick up from the posted documents.
Labor Requirements:
· Project Stabilization Agreement per Appendix F.
· Skilled & Trained workforce requirements per Appendix C.
Schedule:
· 3 phases per “Appendix A – Project Description, Schedule, Phasing”.
· Design & Permitting: 9/1/2025 – 6/1/2026.
· Construction: 6/1/2026 – 7/30/2028.
Alternates & Unit Pricing:
· Additional solar PV panels per project documents.
· Hazmat unit pricing per “Attachment 1 Hazardous Material Abatement Specification” located in Appendix B – HAZMAT pages 63 – 64 of 182.
Warranty:
· 2 years.
Items to be Salvaged (per Appendix C – Special Conditions 00 73 13-8):
Existing improvement and equipment identified below need to be properly disconnected, removed and delivered to the District maintenance yard prior to identified buildings to be demolished.
· Fire Alarm devices such as strobes, smoke detectors and heat detectors
· Exterior Speakers
· Exterior WAPs with Cover Boxes
· Interior Clock/Bell Speakers
· Key cores from door hardware
· Fire Extinguishers
· Interior WAPs
· Interior Projectors, Projector Mounts and Project Screens
· IDFs & MDF
Additional Information:
· Review “Appendix C – Special Conditions” for additional requirements.
Disabled Veteran Business Enterprise (DVBE) participation is encouraged.