The Lopes Road Lift Station Improvements Project includes
various modifications and upgrades to existing features of the project site. Work includes, but is
not necessarily limited to, demolition and disposal of existing sewage pumps and piping (and
related appurtenances); demolition of disposal of existing electrical and instrumentation
equipment; demolition, repair, and construction various concrete and structural components;
and installation of replacement pumps, piping, and equipment in accordance with Contract
requirements as specified herein and indicated on the Drawings. As an active raw sewage lift
station, scheduling of activities and use of temporary systems are integral components of
successfully completing the work.
The WORK must be completed within five hundred (500)
calendar days after the commencement date stated in the Notice to Proceed.