The work includes, but is not limited to:
• Construction of a new sodium hypochlorite storage and metering facility;
• Installation of District provided storage tanks in the new storage facility;
• Construction of a new sodium hypochlorite fill station and delivery truck pad;
• Demolition of an existing sodium hypochlorite storage and metering facility;
• Installation of new fiber optic system components
• Related demolition, site improvements, process equipment, electrical and instrumentation
systems, and incidentals as described in the Contract Documents.
The successful bidder will have 585 calendar days to substantially complete the project.