Scope of work includes the following key activities at a wastewater treatment plant. Excavation and construction of a concrete pad to support new equipment, installation of a Gas Conditioning System on the newly constructed concrete pad, installation of biogas and natural gas pipelines to integrate with existing infrastructure, installation of electrical systems, instrumentation and control components to support the operation and monitoring of the new system.
The Work under this Contract includes the installation of a new, pre-purchased gas
conditioning system manufactured by Unison Solutions Inc. This system will be used to treat
digester gas produced by existing anaerobic digesters. The cleaned digester gas will be
conveyed to linear generators, which are being furnished and installed under a separate
contract. All work shall be completed in accordance with the Contract Documents, Drawings, and Technical Specifications.
Engineer’s Estimate: $5,500,000
Disadvantaged business (DBE) participation is encouraged.
Substantial Completion of this Project shall be completed within Three Hundred and Two (302)
consecutive days from the date established in the Notice to Proceed.