This project includes furnishing all labor, materials, tools, transportation, equipment, and temporary construction required to perform and complete all work for the Digester 3 Rehabilitation and Digester Gas Piping Replacement Project (CIP #9244) project as shown and specified in the contract documents. Work shall include all material, labor, equipment, and apparatus, whether specifically mentioned or not, necessary to complete the specified work.
Work includes but is not limited to:
a. Removal of existing protective coatings and providing new protective coatings.
b. Removal and replacement of an existing coated foamed roofing system on a steel digester cover.
c. Removal of existing piping, equipment, and supports and installation of new piping, equipment, and supports including valves, fittings, and digester gas management equipment.
d. Replacement of the perimeter seal on an existing fixed, steel digester cover.
e. Construction of miscellaneous electrical and controls improvements.
f. Modification of existing digester cover support brackets.
g. Spot repair of existing protective coatings.
h. Spot repair of existing concrete.
i. Installation of aluminum grating and support systems.
j. Installation of temporary digester gas piping.
k. Lining of existing piping.
Disadvantaged Business Enterprise (DBE) participation is encouraged.
Substantial Completion of this Project shall be completed within 350 (three hundred and fifty) consecutive days from the date established in the Notice to Proceed for the commencement of Contract Time.