Bid Details for MERCED WWTF PHASE VI PROJECT – ASD SUPPLEMENTAL HEATING SYSTEM AND HEADWORKS IMPROVEMENTS

Project
MERCED WWTF PHASE VI PROJECT – ASD SUPPLEMENTAL HEATING SYSTEM AND HEADWORKS IMPROVEMENTS
Owner
CITY OF MERCED
Description

DESCRIPTION OF THE WORK: The work to be performed includes but not limited to the
construction of a new Boiler Building, gas treatment system, hot water boilers, pumps, compressors,
piping and electrical for the Active Solar Dryers (ASDs) Supplemental Heating System; influent flow
meter manhole; and new mechanical screens, washer/compactors, grit removal baffles, new
equipment hatches, flap gates, piping, electrical, and concrete repair for the Headworks
Improvements.
Work inside the ASDs, except for piping and electrical, will be by the Owner selected manufacturer’s
representative that will also furnish some of the equipment and materials of construction inside the
dryers and will furnish the boilers and electrical motor control center (MCC) for the dryer equipment
located inside the Boiler Building. The Contractor selected for this project will install the furnished
boilers and MCC and will furnish and install all other equipment, piping and electrical.
The Owner has selected the manufacturer of the mechanical screens and washer/compactors at
the Headworks. The Contractor selected for this project will furnish and install all equipment and
electrical for the mechanical screens and washer/compactors.
Such other items or details, not mentioned above, that are required by the Drawings and Technical
Specifications Plans, City of Merced Standard Specifications and Typical Details, and the Special
Conditions shall be performed, placed, constructed, or installed.

LOCAL BUSINESS ENTERPRISE (LBE) 5% PARTICIPATION is encouraged.  See additional details mentioned in the requirements below and in the specifications.

The work shall be Substantially Completed within 220 working days of Notice to Proceed and shall be Final Completed and accepted by the City within 90 working days after Substantial
Completion.

Trades include, but are not limited to; demo, dewatering, earthwork, excavation, ac paving, concrete, concrete saw-cutting and core-drilling, epoxies, masonry, structural steel, steel deck, metal fabrications, gratings, stair treads, and floor plates, gypsum sheathing, waterproofing, flashing and sheet metal, roof and deck insulation, joint sealer, steel doors and frames, overhead coiling doors, skylights, door hardware, glazing, metal lath, plastering, painting, fire extinguishers, misc. municipal equipment, mechanical and electrical.

Location
City of Merced Wastewater Treatment Facility (\!WI/TF), 10260 Gave Road, Merced, CA 95340.
Amount
$11.6M
Bid Walk

PRE-BID CONFERENCE – Wastewater Treatment Plant located at 10260 South Gove Road, Merced, CA 95340 on January 25 at 10:00 a.m. per addendum #1

Requirements
LOCAL BUSINESS ENTERPRISE (LBE) PARTICIPATION Local Business Enterprise (LBE): An LBE is defined as a business firm with a valid non-delinquent City of Merced business license and with fixed offices or distribution points within the County of Merced. Certification as an LBE: A business is automatically considered a certified LBE with the City of Merced if the business has a permanent physical location within Merced County and has an active City business license.
Availability
OBTAINING OR INSPECTING CONTRACT DOCUMENTS: Printed copies of the plans are available at the City of Merced at 678 W. 18th Street Merced, CA 95340. Digital copies of the plans and specifications may be obtained from the City of Merced Engineering Department by sending an email to Taylor Gates (GatesT@cityofmerced.org). Fee for digital copy is $100 or hard copy is $300.