Bid Details for LLNL New Employee Center

Project
LLNL New Employee Center
Owner
Lawrence Livermore National Laboratory (LLNL)
Bid Time
01/24/2025 2:00 pm
Description
Lawrence Livermore National Laboratory (LLNL) has a need for employee meeting space and fitness and enrichment activities at Site 200 location central to the LLNL population. This facility will replace currently used locations in aged facilities.
 
The objective of the project is to abate and demolish existing trailer (T4675) and build a new ~23,500 gross square foot ground-up two-story fitness and amenity Employee Center building and associated site improvements. The work includes, but is not limited to abatement, demolition, grading, earthwork, site utilities, paving and drive aisles, concrete foundation and slab, concrete masonry unit and framed exterior walls, insulated metal panel wall system, storefront and cuirtain wall window system with insulated low-E glass, structural steel roof framing and columns, single-ply roofing system over rigid insulation over metal decking, elevator, stairs, stud framed interior walls and gypsum board, tile work, lockers, framed and suspended interior ceiling systems, rooftop mechanical system, plumbing system, and electrical power and lighting systems.
 
Additionally, the project will feature a steel and aluminum trellis system, landscaping, site furnishings, planting, irrigation, and bio-swales.
 
The New Employee Center, building 460, will bring many opportunities for meeting/event space, fitness, employee engagement, networking, and work-life programs at the Livermore Campus.
 
This project includes three alternates and two options. Alternates may be selected at time of award. Options may be selected up to 180 days after award.
 
  • Additive Alternate 1: Motorized interior operable partition at Multi-purpose Room.
  • Additive Alternate 2: Interior ceiling fans and associated infrastructure at Gym, Cardio, Large Group Fitness, Cycle, and Dance rooms. (Note that base scope does not include the infrastructure.)
  • Additive Alternate 3: Provide Solarban 70XL Glass with Aviproteck E Acid Etching (Pattern 215) on surface #1 at all glazing.
  • Option 1: Outdoor fitness area and associated amenities: artificial turf, fencing, gate with panic hardware, lighting, speakers.
  • Option 2: Additional hardscape at the east side of the site, trellis, site furniture, community table, built-in bar-height table.
 
See PRD for owner furnished items including but not limited to 750kVA 13.8kV – 480/277V pad-mount transformer.
 
 
Location
Lawrence Livermore National Laboratory, site 200, 7000 East Avenue, Livermore, CA 94550
Amount
Bid Walk
Requirements
Availability
www.buildingconnected.com login is required Contact bids@overaa.com for access.