The Work consists of, in general, 1) installing IX
treatment to remove PFAS from groundwater and 2) improving Chain of Lakes Well No. 1
site to support the PFAS treatment system. Contractor shall furnish and install all new
equipment as specified in the Contract Documents. Contractor shall comply with all
required Alameda County Health Orders, including those for COVID-19. Bidding
Documents contain the full description of the Work.
Work shall be finally completed within 457 Calendar Days
from the date when Contract Time commences to run.