CCCSD Electric Blower Improvements & Treatment Plant Piping Renovations, Phase 10

Owner: 
Central Contra Costa Sanitary District (CCCSD)
Bid Date: 
Wednesday, June 16, 2021 - 17:00
Description: 

The Electric Blower Improvements Project generally consists of major structural, mechanical, electrical, instrumentation, and controls upgrades to existing
and new electric blowers, chillers, filter houses, and related auxiliary facilities. The Treatment Plant Piping Renovations, Phase 10 Project generally consists of
improvements to the 1-Water system, rehabilitation and improvements to the sodium hypochlorite system, and replacement of electrical equipment and piping.

 

The Contract Time for the completion of all the Work of the Project is four hundred and forty (440) Calendar Days.

Location: 
5019 Imhoff Place, Martinez, CA 94553
Amount: 
$13,800,000
Estimator: 

Larry Etcheverry (510)234-0926

larrye@overaa.com

Bid Walk: 
See details below
Bid Walk: 

Pre-bid documents and video will be made available on PlanetBids Tuesday, May 25,
2021. No pre-bid meeting will occur. Any bidder that would like to access the project
site pre-bid, may by appointment only. Appointments will only be available on
Wednesday, June 2, 2021, at 9:00 a.m. or 10:00 a.m. To schedule an appointment,
please contact Nancy Molina at 925-335-7794 or nmolina@centralsan.org. No
exceptions to this requirement.

Availability: 

Complete sets of Contract Documents and related Supplemental Project Information
Available to Bidders can be downloaded from PlanetBids
http://www.planetbids.com/portal/portal.cfm?CompanyID=14663#