Seismic repairs and access modifications to a five-level, 800-stall garage within a five month accelerated schedule. Scope included new shear walls, crack repair, the addition of fortifying steel plates, a new elevator, and a new pedestrian bridge. The parking structure was kept operational throughout construction. We developed a detailed phasing plan, by floor and by area, to ensure minimal impact to the student and faculty users. We scheduled activities around the academic calendar to further minimize student inconvenience.

Owner
San Francisco State University
Location
San Francisco, CA
Engineer
The KPA Group
Levels
5
Stalls
800
Square Feet
541,500